GOLIATH must be started before DAVID.
DAVID must be stopped before GOLIATH.
It is not possible to ramp up DAVID as I ref DAVID > I GOLIATH
All power converters (NR31-01, NR31-05, NR31-06) must be in the same polarity.
General Documentation
NR31-01 FESA parameters :
ADC Nominal Current : 3276.6
DAC Nominal Current : 2250
Converter topology : single
Equipment Magnet Current Max : 3600
NR31-06 FESA parameters :
ADC Nominal Current : 3276.6
DAC Nominal Current : 2500
Converter topology : single
Equipment Magnet Current Max : 2500